TL;DR
Wallonia ordered Google to suspend construction at its planned data centre in Farciennes, saying a three-hectare building lacked proper planning permission. Google says work is paused while it awaits further guidance; its court challenge over a rejected water-cooling permit is due for a hearing in January.
Wallonia’s regional authorities have ordered Google to suspend construction at its planned data centre in Farciennes, southern Belgium, saying a three-hectare building was built without proper planning permission. Google told the BBC it had paused work while awaiting further guidance, as a separate dispute over the site’s proposed water-cooling plan is set to go before a court in January.
Get everyday essentials delivered free with Prime
- Fast, free delivery on millions of items
- Prime Video, Amazon Music and more included
- Member-only deals all year
Regional inspectors visited the site on Thursday and told Google representatives to halt construction, the regional authority said. Nicolas Yernaux, a spokesperson for the Walloon authorities, described the alleged breach as “a major offense” involving the construction of a building covering three hectares. AFP reported his account on November 27.
The order concerns the building’s planning status. The authorities have said it lacked proper permission, while Greenpeace Belgium separately alleged that work continued after a permit version was revoked. Google’s response, as reported by the BBC on November 29, was that it had paused the work “pending additional guidance” and remained committed to complying with local laws.
The site’s cooling plans are also contested. Google applied to change the project from air cooling to a system using water from the nearby River Sambre. Regional officials refused that application over the summer, after a dry spring heightened concern about drawing water from the river, according to AFP. Google has challenged the refusal in court; a hearing is scheduled for January.

Water and Permits Shape the Project
The dispute shows how planning approval and water access can affect the schedule of a large computing project. A stop-work order can hold up construction while authorities and the company address whether the building has the required permission. The separate court case may determine whether Google can use its proposed cooling method.
Data centres house computers that run online services and AI systems, and those machines produce heat that must be managed. The Farciennes reports do not say how much water Google’s proposed system would use, or how the order will affect the project’s overall timetable. For now, the confirmed effect is that authorities have ordered construction to stop and Google says work is paused.
Popular right now

Ninja CREAMi Scoop & Swirl 13-in-1 Ice Cream and Soft Serve Maker, NC701

Breville Barista Express Espresso Machine with Built-In Grinder, Black Truffle

Ninja Foodi Power Blender & Processor System, 7 Functions, Silver, SS401
As an affiliate, we earn on qualifying purchases.
How the Cooling Dispute Developed
The project was initially planned with air cooling, according to Belgian media cited by AFP. Google later sought permission to use water from the Sambre instead. Regional officials rejected the requested change over the summer. Google then challenged that refusal in court, with a hearing scheduled for January.
Separately, Greenpeace Belgium said in a report this week that drone footage showed construction continuing. The group said the latest version of the planning permission had been revoked in August. Those statements are Greenpeace’s account; the regional authorities have separately said inspectors found a building without proper permission and issued the stop-work instruction. The reports available do not include the order itself.
AFP also reported in October that Finnish authorities had halted work at two Google data centre sites there. That is separate from the Belgian case and does not establish the status or cause of any other project. In Farciennes, the current dispute centers on the building’s planning permission and Google’s rejected request to change its cooling plan.
““Pending additional guidance.””
— Google, as reported by the BBC
The Order’s Full Scope Is Unclear
The reports do not include a copy of the stop-work order, so its full terms and any conditions for resuming construction are not clear. It is also unknown whether the building can later be legalised, what response Google may make to the planning-permission allegation, or how long the pause could last.
The amount of water the proposed cooling system would require has not been reported in the source material. The January hearing concerns Google’s challenge to the refusal of its water-cooling application; the available reports do not establish whether that case will resolve the separate allegation about construction permission.
January Hearing Will Test Water Plan
The next scheduled milestone is the January court hearing on Google’s challenge to the regional refusal of its water-cooling request. The company says construction is paused while it awaits further guidance. Any decision on the court challenge, and any further direction from regional authorities about the building, could clarify what can proceed at the site.
Until those steps occur, the order remains the immediate constraint on construction, according to the reporting available as of November 29. The duration of the pause and the project’s eventual cooling arrangements remain unknown.
Key Questions
Why did Wallonia order Google to stop construction?
Regional authorities said a three-hectare building at the Farciennes site was constructed without proper planning permission. Google says it has paused work while awaiting further guidance.
What is the dispute over the River Sambre?
Google sought to change the site’s planned cooling system from air to one using water from the River Sambre. Regional officials refused the request over the summer, and Google challenged that decision in court.
When is Google’s court hearing?
A hearing on Google’s challenge to the rejected water-cooling application is scheduled for January. The reports do not say whether that hearing will also address the building’s planning-permission status.
Has Google confirmed that work has stopped?
Google told the BBC that it had paused work pending additional guidance. Greenpeace Belgium had alleged that construction was continuing, citing drone footage. The available reporting does not include the order itself or a later independent site inspection.